UNDCP I.R. Iran - PROJECT MONITORING SHEET Annex 3 |
PROJECT AD/RER/C38
| Starting date: | July 1999 |
| Duration: | 30 Month (July 1999 – December 2001) (phase I) |
| Total budget: | US Dollars 155,750 |
| Source of UNDCP funding: | EC & Japan |
| Executing Agency: | UNDCP Associated Agency: UNOPS |
| UNDCP Project Officer: | Mr. Kaveh Moradi |
| National Project Coordinator: | Drug Control Coordination Unit. |
| DCCU Project Officer: | Mr. Celalettin Martin (till December 2000) |
| IMMEDIATE OBJECTIVE: | Creating a Drug Control Coordinating Unit (DCCU) at the ECO Secretariat and coordinating its activities and operation with the ECO Member States. |
|
OUTPUT |
ACTIVITIES |
WORKPLAN |
VER |
PROBLEMS & SOLUTIONS |
FINAL OUTPUT |
||||
|
SCH |
COMP |
PROBLEM |
SOLUTION |
SRC |
VER |
||||
|
Output 1: DCCU is to be involved in 18 months pilot coordination and planning among the ECO Member States.
|
Activity 1.1: a) Organizing & debriefing session by UNDCP consultant to ECO Members. b) NPO & PA contracts started
Activity 1.2: ECO/DCCU is physically installed. Expendable & non-expendable equipment purchased.
Activity 1.3: ECO/DCCU is officially opened.
Activity 1.4: ECO Member States focal points appointed.
Activity 1.5: ECO Member States drug control information is submitted.
Activity 1.6: DCCU officers’ basic computer and internet training
Activity 1.7: Semi-annual progress report is prepared and forwarded to UNDCP and EC HQs in Brussels.
Activity 1.8 & 1.9: Organization of Task Force Meeting 1 and 2 including consolidated agenda and invitations.
Activity 1.10: Task Force Meetings conclusion formulated
Activity 1.11: ECO staff to visit ECO Member States.
Activity 1.12: Preparation of draft country profiles (Document 1) and consolidated report (Document 2)
Activity 1.13: Document 2 (country profiles) and 3 (consolidated report) forwarded to national focal points for their comments and appear at DCCU website.
|
7.1999
7.1999 to 6.2000
7.1999 to 12.1999
7/1999
8.1999 to 1.2000
1 to 7 ,2000
10.1999 & 3.2000
6/2000
3.2000
3.2000
8 to 9,1999
10.1999 to 1.2000
11 to 12, 1999 |
7.1999
10/2000
10/2000
7/1999
10.2000
10. 2000
10.1999 & 3.2000 1/2000
2.2000
3.2000
4 to 5, 2000
10.2000 |
RT
NN
NN/ RT
RT
RT
RT
RT
RT
RT
RT
RT, NN, FP
RT |
Long delay in MS appointment.
2 MS delay submitting reports
Arrangement with MS very time consuming
Lack of timely coordination among MS and PO
PO not able to provide report according to Schd. |
Continued follow ups with MS MFAs and local embassies Continued follow ups with MS MFAs and local embassies
Continued follow ups with MS MFAs and local embassies.
PO to prepare Doc. 1 & 2 before end of 1st phase
Output shifted to 2000
|
PO/ FO
PO
PO/ FO
PO
PO/ FO |
PO
PO
PO/ FO
PO/ FO
PO/ FO |
All national focal points appointed
Information flowing to DCCU Focal Points appointed.
Task completed.
Task completed.
Task completed.
Task completed
Missions by DCCU project coordinator and ECO computers expert to all ECO countries
Task completed.
Report on missions produced and circulated to all ECO MSs, DCP HQs and EU
Reports finalised and forwarded. |
|
|
Activity 1.14: DCCU establishes internship programme
Activity 1.15: DCCU secured website developed.
Activity 1.16: Website address and secure password are disseminated to donor community.
Activity 1.17: Setting up of DCCU ECO Member States computerized network (purchasing, installing computer equipment –training)
Activity 1.18: ECO staff missions to UNDCP HQs, ICPO – Interpol HQs, & CCM.
Activity 1.19: Discussion between UNDCP & ECO/DCCU for second support phase of the project and formulation of project with UNDCP assistance
Activity 1.20: PPER drafted with assistance of UNDCP office (and forwarded to EC HQs)
Activity 1.21: Consolidated reports and country profiles are published at website and disseminated.
Activity 1.22: Glossary of drug control institutions in ECO region is prepared
Activity 1.23: The glossary and DCCU Task Force Meetings’ conclusions published on website.
Activity 1.24: Drafting and publication of the 1999-2000 Regional Drug trends publication
Activity 1.25: Updating country profiles.
|
10.1999 to 7.2000
10 to 12, 1999
12, 1999
12,1999
10.1999
7 to 10, 2000
7,2000
5 to 7, 2000
3, 2000
3, 2000
3 to 5, 2000
5 to 7, 2000 |
5.2000 to 7.2000
1.2001
7,2000
8, 2000
12.2000
12.2000
|
NN
RT |
Technical problems in receiving countries As above
As above
PO not completed the activity due to delays in other activities
PO not completed the activity
PO not completed the activity due to delays in other activities |
The secure site has been replaced by normal site. Full secure site shifted to 2nd phase A DCCU ECO web site will be established pending the setting up of the secure web site Activities shifted to 2001due to tech. complexity and timing req.
Activities shifted to 2nd phase due to tech. complexity and timing req.
FO prepared the PPER
Activities shifted to 2nd phase due to tech. complexity and timing req. |
PO/ FO
PO/ FO
PO/ FO
PO/ FO
FO
PO/ FO |
PO/ FO
PO/ FO
PO/ FO
FO
PO/ FO |
Task completed.
Activity moved to Phase II.
Activity moved to Phase II
Activity moved to Phase II.
Activity moved to Phase II.
Project Proposal finalised/approved by ECO MS and forwarded to HQ and EC.
Activity moved to 2001/2nd phase
Task completed.
Activity moved to 2001/2nd phase
Task completed.
Draft updates forwarded to Member States and UNDCP HQ |